Grout Pumps Reciprocating Type, Cement Grout Pumps, Expansion Joint Filler Board, Compressible Debonding Strips, Thane, India

   Grout Pumps Reciprocating Type, Cement Grout Pumps, Epoxy, P.U., Grout Pump, Expansion joint filler board, Compressible Debonding strips, Pressure Grounting, Roads, Highway, Runway, Crack Treatment, Grouting, Thane, India
   
Since then we have offered the following services to various industries :


Water Proofing

Protective Coating

Anticorrosive Coating

High build Coating for Uranium Disposal Plant

Floor Coating

Expansion Joints

Structural Strengthening of Buildings

Pavement Joints

PQC Repairs

Grouting in Tunnels (Cement, Epoxy, PU)
 


 

   WORK FORCE & EQUIPMENTS ----- A GLIMPSE
 

GROUT PUMPS RECIPROCATING TYPE. CEMENT GROUT PUMPS.
CAPACITIES 1Kg / SQCM TO 20Kg / SQCM. DELIVERY 1 BAG / HR TO 200 BAG / HR.

Cement grout pump.

Cement grout pump

USED AT IPS-BANDRA TUNNEL & GHATKOPAR HIGH LEVEL TUNNEL.

HIGH DELIVERY RATE & LOW WORKING AREA.
DELIVERS 20 TO 50 BAGS /HR
AT 10KG/SQCM
EPOXY / P.U . TWO / THREE COMPONENT
EPOXY / P.U . TWO / THREE COMPONENT
GROUT PUMP.

AUTOMATIC DOZING. DELIVERS UP TO
2 LTRS / MIN.

PRESSURE
0 - 20 Kg/ SQCM.
MACHINE SPECIALY DEVELOPED FOR
LOW WORKING SPACE AREAS.


USED AT DHARAVI TUNNEL FOR DYWIDAG-
AG & BMC.


SCOPE OF MATERIAL SUPPLY AND EXECUTION
Sr. No. Description Supplied / Executed by
1
Expansion joint filler board Supply by Elcon products
2
Compressible Debonding strips Supply by Elcon products
3
Temporary seal of 8 mm rod Supply by Elcon products
4
Green concrete-saw grove 4mm X 110 mm Execution by Eff-tech
5
Widening of grove to 8 / 10 mm Execution by Eff-tech
6
Sealant application (silicon,P.U.,Polysulphide,etc) Execution by Eff-tech
7
Sealant (silicon,P.U.,Polysulphide,etc) Supply by Elcon products
8
Pre formed seal (Neoprene seal) Execution by Eff-tech
9
Pre formed seal (Neoprene seal) Supply by Elcon products

Schedule of grove cutting :

1. Initial cutting is carried out at green-concrete stage.
2. Final cut is done after 21 to 28 days.
3. Sealant is done on bone dry surface, generally after 1 or 2 days, i.e. between 30th and 35th day.

We help you in selecting & negotiating sealant manufacturers, also we optimize sealant consumption to suit & qualify various tests at site. We conduct field test on trial patch to technically ratify the sealant suitability.

We also undertake complete contract with sealant.

Back  | Next